Korea Western Power Company Limited (KOWEPO) has published a tender for the purchase of 1,550,000 MT Steaming Coal for Korean Genco’s Power Plant.
The bidder is requested to offer in lots of 130,000MT for JT-01 and 80,000MT for JT-02 on FOBT basis only. Regardless of above quantity for each Genco, the final unit quantity can be changed as per Genco’s request(from 110,000MT to 150,000MT for JT-01 and from 70,000MT to 80,000MT for JT-02) with ten(10) percent of shipping tolerance being given.
Quantity and Delivery Period :
| No | Spec(NCV) | Quantity | Delivery Period (Loading Port) |
| JT-01 (HCV) |
Min.5,700kcal/kg (TS : 0.8% max) |
910,000MT +/-10% (7 Capes) |
June 2019: 2 shipments July 2019: 4 shipments August 2019: 1 shipment |
| JT-02 (LCV) |
Min.4,600kcal/kg (TS : 0.6% max) |
640,000MT +/-10% (8 Panamax) |
June 2019: 5 shipments July 2019 : 3 Shipments |
Specification:
| Technical Parameters | JT-01 | JT-02 |
| Total Moisture (As received basis) | Max 15% | Max. 28 |
| Total Sulphur (As received basis) | Max 0.8 | Max 0.6 |
| Net Calorific Value (As received basis) | Min 5,700 | Min 4,600 |
| Ash Fusion Temperature | Min 1,200 | Min 1,200 |
Due date (Korean Standard Time): The due date for bid submission is 28 Mar’19 till 10:00 Hrs.