Korea Southern Power Co Ltd (KOSPO) has published a tender for purchase of steam coal of quantity 240,000 MT for Samcheok power plant, South Korea.
Each bidder is requested to offer min 160,000 MT in lots of 80,000 MT on FOBT basis.
The shipment shall be scheduled between January and March 2018.
Supply of coal from more than one mine is not allowed,
Specification:
|
Technical Parameter |
Value |
|
Total moisture (as received basis) |
Max. 43 |
|
Fixed carbon (air dried basis) |
Max. 60 |
|
Ash (air dried basis) |
Max. 4.5 |
|
Net calorific value (as received basis) |
Min. 3,700 kcal/kg |
|
Ash fusion temperature |
Min. 1,050 |
The offer given by the bidder shall be valid for the period 3 days from the date of tender closing. Although if necessary KOSPO can request the bidder to extend validity period of bid.
Due date:
The due date for bid submission is 29 Nov’17 at 14:00 hrs (Korean Standard Time).
For Tender Documents and Other Details CLICK HERE