Nabha Power Limited (NPL), a subsidiary of L&T has invited a tender for the purchase of 900,000 MT imported non-coking coal at its Rajpura Thermal Power Plant, Punjab on ‘delivered to the plant’ basis.
The power company had previously floated a coal purchase tender for 3 LT (Lakh Tonne) of 4800 GAR specification, which was scheduled on 21 Feb’19.
This time the company has invited tender for coal ranging from 5000-5700 GAR, up to 9 Lakh Metric Tons uniformly distributed with weekly delivery schedule throughout the period till 31stDec’19.
Specification
| Technical Parameters | A1 5700 GAR Base GCV | A2 5000 GAR Base GCV |
| Total moisture | 18% Max | 20% Max |
| Ash | 26% Max | 29% Max |
| Volatile matter | 20-27 % | 20-27 % |
| Sulphur | <=0.5% | <=0.5% |
| GCV (GAR) A type coal | 5700-5000 Kcal/kg | 5000-4400 Kcal/kg |
Tender schedule (IST): The due date for submitting the bids is 9 May’19 till 11:00 hrs and the opening of the bids is scheduled on the same day at 11:30 Hrs.
For contact details view TENDER SECTION.