- JSW is ramping up production at Dolvi.
- 5 mn t/year brownfield project at Vijayanagar shall be completed by FY’24.
- Commissioning of the second line at CRM-1 at Vijayanagar likely by Q3FY’22
- 0.45 mn t/year galvanising line at Vasind to be commissioned in Q3 FY’22.
- 0.5 mn t/year continuous annealing line to be commissioned by Mar’22.
- Second 0.25 mn t/year tin plate line at Tarapur likely to commence by Jun’22.