The Taiwan Power Company (Taipower) is a state-owned electric power utility providing electric power to Taiwan and off-shore islands of Republic of China, has invited a limited tender for purchase of 800,000 MT general sub bituminous coal for Taipower thermal power plant.
General conditions:
1. Delivery period is from Sep’17 to Dec’17.
2. The material shall be shipped by 10 Panamax size vessels, each carrying 80,000 MT+/-10%.
3. Bidder may offer one or more shipments.
4. The bid bond is USD 80,000 or TWD 2,596,000 per shipment.
Specification:
| Value | |
| Gross calorific value | 5,000 kcal/kg min |
| Total moisture | 28% max |
| Ash content | 8% max |
| Sulphur content | 0.9% max |
| Volatile matter | 28% min |
| Fixed carbon | 60% max |
| Mercury content | 0.12 mg/kg max |
Tender schedule:
Bid submission due date: 24 July’17 at 17:00 hrs (Taipei time)
Bid opening date: 25 July’17 at 9:30 hrs (Taipei time)
For contact details view tender section:
http://www.steelmint.com/tender/global-tender-for-purchase-of-bituminous-coal-8069

Leave a Reply